Substation Scout

Kankakee substation interconnection queue

2 active projects totaling 70 MW in the PJM queue, plus 5 with terminal status (shown grayed).

7 PJM queue filings name Kankakee as the point of interconnection, all in IL.

Target commercial operation dates as filed run from Jun 2007 to May 2026 (7 filings).

2active projects
70active MW
7total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI2-076 Kankakee 138 kV 138 56 Wind Withdrawn Mar 2023
S36 Kankakee Wind Farm 138 35 Wind In Service Jun 2015
S37 Kelly Creek Wind Farm 138 35 Wind In Service Dec 2016
U2-065 Kankakee 138kV 138 32.5 Wind Withdrawn Sep 2012
AI2-014 Kankakee 138 kV 138 20.5 Solar Withdrawn May 2026
AD1-150 Kankakee 34.5 kV 34.5 4 Battery Withdrawn Jul 2019
Q13 Kankakee 12kV 12 1.6 Gas Withdrawn Jun 2007

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Kankakee County, IL

All 42 PJM queue filings in Kankakee County, IL.

Other PJM queue substations in Iroquois County, IL

No other substation in Iroquois County, IL is named as a point of interconnection in the PJM queue.

All 2 PJM queue filings in Iroquois County, IL.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first