Fayetteville substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 5 with terminal status (shown grayed).

5 PJM queue filings name Fayetteville as the point of interconnection, all in Franklin County, PA.

Target commercial operation dates as filed run from Dec 2021 to Dec 2022 (5 filings).

0active projects
0active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE1-188 Fayetteville Solar 34.5 12.6 Solar Withdrawn Mar 2022
AE2-269 Fayetteville 138 kV 138 9.2 Solar Withdrawn Dec 2021
AF1-151 Fayetteville 34.5 kV 34.5 8.4 Solar Withdrawn Dec 2022
AF1-224 Fayetteville Solar 34.5 7.9 Solar Withdrawn Mar 2022
AF1-061 Fayetteville 12.47 kV 12.5 1.2 Solar Withdrawn Dec 2021

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Same name on other Substation Scout pages

Other sources that print a substation named “Fayetteville” in PA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.

Other PJM queue substations in Franklin County, PA

All 80 PJM queue filings in Franklin County, PA.