Substation Scout

Morris, NJ interconnection queue

3 active projects totalling 14.8 MW in the PJM queue, plus 19 with terminal status (shown greyed).

3active projects
14.8active MW
22total filed
Queue IDProjectkVMWResourceStatus
Q41 Mt Hope Waterpower Project 34.5 30 Other Withdrawn
AF1-008 CPV NJ Solar n/r 8.4 Solar Withdrawn
AF1-145 Flanders-Netcong 34.5 kV 34.5 8.4 Solar Withdrawn
AF2-138 Mount Olive Solar Farm 34.5 8.3 Solar In Service
AG1-191 South Combe 34.5 6.5 Solar In Service
U3-032 Britton Road Solar Facility 34.5 6.5 Solar Withdrawn
X1-094 Mount Olive Solar Farm 34 6.4 Solar Withdrawn
V3-005 Morris 34.5kV 34.5 3.8 Solar Withdrawn
V4-004 Roxbury 12.5kV 12.5 3.8 Solar Withdrawn
X1-048 Kenvil 12.5kV 12.5 1.5 Solar Withdrawn
W1-059 Denville n/r 0.8 Solar Withdrawn
X1-034 Renaissance at Hanover Solar Farm 12 0.5 Solar Withdrawn
W2-006 Newburgh 12kV 12 0.4 Solar Withdrawn
W3-006 Newburgh 12kV 12 0.4 Solar Withdrawn
AC1-084 Mt. Arlington Solar n/r 0 Solar Withdrawn
AC1-218 Not reported n/r 0 Battery Withdrawn
AC1-219 Not reported n/r 0 Battery Withdrawn
AC2-145 94-98 Ford n/r 0 Battery Withdrawn
AC2-175 Berkshire Solar 12 0 Solar In Service
AD2-210 South Jefferson Road Storage 12.5 0 Battery Withdrawn
AF1-324 Denville Storage Facility 34.5 0 Battery Withdrawn
AG2-531 Greystone - West Denville 34.5 kV 34.5 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.