Red Lion substation interconnection queue
3 active projects totalling 588.3 MW in the PJM queue, plus 2 with terminal status (shown greyed).
3active projects
588.3active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| D15 | Red Lion 500kV | 500 | 550 | Gas | Withdrawn |
| B47 | Hay Road 5, 6, 7 | 500 | 545 | Gas | In Service |
| D14 | Red Lion 500kV | 500 | 190 | Gas | Withdrawn |
| X1-097 | Red Lion Energy Center | 138 | 23.3 | Other | In Service |
| T52 | Hay Road Units 5, 6, 7, 8 | 500 | 20 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.