Substation Scout

Townsend substation interconnection queue

1 active project totalling 37.6 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
37.6active MW
3total filed
Queue IDProjectkVMWResourceStatus
AB2-179 New Castle Solar 138 37.6 Solar In Service
AB2-182 Townsend 25kV 25 14 Solar Withdrawn
W3-086 Townsend 138kV 138 3.8 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.