Substation Scout

Glory substation interconnection queue

1 active project totaling 6 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Glory as the point of interconnection, all in PA.

Target commercial operation dates as filed run from Jan 2000 to Dec 2025 (2 filings).

1active projects
6active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI1-115 Glory 34.5 kV 34.5 9.9 Hybrid Withdrawn Dec 2025
A10 Colver Power 115 6 Coal In Service Jan 2000

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Glory (PENELEC, 11 mentions).

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Other PJM queue substations in Clearfield County, PA

All 53 PJM queue filings in Clearfield County, PA.

Other PJM queue substations in Cambria County, PA

All 46 PJM queue filings in Cambria County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first