Cambria Slope substation interconnection queue

1 active project totalling 200 MW in the PJM queue, plus 5 with terminal status (shown greyed).

1active projects
200active MW
6total filed
Queue IDProjectkVMWResourceStatus
AD1-127 Cambria Slope 115 kV 115 235 Gas Withdrawn
C01-1175 Cambria Slope 115 kV 115 200 Battery Active
M22 Cambria Slope 115kV 115 125 Coal Withdrawn
AJ1-016 Cambria Slope 115 kV 115 100 Battery Withdrawn
N28 Cambria Slope 115kV 115 40 Coal Withdrawn
AE1-165 Cambria Slope 115kV 115 12 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.