Substation Scout

Harvey Run substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Harvey Run as the point of interconnection, all in Clearfield County, PA.

Target commercial operation dates as filed run from Nov 2023 to Dec 2023 (2 filings).

Transmission owner as filed: PENELEC (1 filing).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF1-274 Harvey Run 115 kV 115 51 Solar Withdrawn Dec 2023
AG2-668 Harvey Run 34.5 kV 34.5 12.5 Solar Withdrawn Nov 2023

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Harvey Run (PENELEC, 5 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Clearfield County, PA

All 53 PJM queue filings in Clearfield County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first