Substation Scout

La Paz, AZ interconnection queue

0 active projects totaling 0 MW in the APS queue, plus 11 with terminal status (shown grayed).

0active projects
0active MW
11total filed
Queue IDProjectkVMWResourceStatus
Q69 Not reported 230 300 Solar Withdrawn
Q523 Not reported 161 250 Solar Withdrawn
Q80 Not reported 69 100 Solar Withdrawn
Q440 Not reported 69 95 Hybrid Withdrawn
Q457 Not reported 69 85 Hybrid Withdrawn
Q441 Not reported 69 70 Solar Withdrawn
Q114 Not reported 69 50 Solar Withdrawn
Q146 Not reported 69 20 Solar Withdrawn
Q94 Not reported 34.5 20 Solar Withdrawn
Q95 Not reported 69 20 Solar Withdrawn
Q99 Not reported 34.5 20 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with APS before relying on these figures.