Substation Scout

Orchard substation interconnection queue

2 active projects totaling 500 MW in the APS queue, plus 5 with terminal status (shown grayed).

7 APS queue filings name Orchard as the point of interconnection, all in AZ.

2active projects
500active MW
7total filed
Queue IDProjectkVMWResourceStatus
Q350 Not reported 230 300 Hybrid Active
Q450 Not reported 230 300 Hybrid Withdrawn
Q513 Not reported 230 300 Hybrid Withdrawn
Q380 Not reported 230 200 Hybrid Withdrawn
Q425 Not reported 230 200 Hybrid Active
Q453 Not reported 230 200 Hybrid Withdrawn
Q462 Not reported 230 100 Hybrid Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with APS before relying on these figures.