Substation Scout

Redhawk Substation substation interconnection queue

1 active project totaling 400 MW in the APS queue, plus 1 with terminal status (shown grayed).

2 APS queue filings name Redhawk Substation as the point of interconnection, all in Maricopa County, AZ.

1active projects
400active MW
2total filed
Queue IDProjectkVMWResourceStatus
Q376 Not reported 500 400 Hybrid Operational
Q476 Not reported 500 200 Hybrid Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with APS before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →