Yavapai, AZ interconnection queue

5 active projects totaling 636 MW in the APS queue, plus 23 with terminal status (shown grayed).

5active projects
636active MW
28total filed
Queue IDProjectkVMWResourceStatus
Q337 Not reported 500 450 Hybrid Active
Q335 Not reported 500 360 Solar Withdrawn
Q545 Not reported 500 360 Hybrid Withdrawn
Q296 Not reported 230 250 Solar Withdrawn
Q447 Not reported 230 250 Hybrid Withdrawn
Q502 Not reported 230 250 Hybrid Withdrawn
Q241 Not reported 230 200 Solar Withdrawn
Q107 Not reported 115 120 Wind Withdrawn
Q286 Not reported 69 100 Hybrid Withdrawn
Q313 Not reported 69 95 Hybrid Active
Q22 Not reported 230 85 Wind Withdrawn
Q485 Not reported 230 75 Hybrid Withdrawn
Q55 Not reported 69 74 Solar Withdrawn
Q339 Not reported 69 53 Hybrid Suspended
Q245 Not reported 69 26 Solar Withdrawn
Q151 Not reported 69 20 Solar Withdrawn
Q171 Not reported 69 20 Solar Withdrawn
Q172 Not reported 69 20 Solar Withdrawn
Q200 Not reported 69 20 Solar Withdrawn
Q215 Not reported 69 20 Solar Withdrawn
Q232 Not reported 69 20 Solar Withdrawn
Q162 Not reported n/r 19 Solar Operational
Q395 Not reported n/r 19 Battery Operational
Q294 Not reported 12 17 Solar Withdrawn
Q194 Not reported 12 16 Solar Withdrawn
Q210 Not reported 12 15 Solar Withdrawn
Q149 Not reported 12 12 Solar Withdrawn
Q71 Not reported 69 10 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with APS before relying on these figures.