Hoodoo Wash substation interconnection queue

4 active projects totaling 1,260 MW in the APS queue, plus 3 with terminal status (shown grayed).

7 APS queue filings name Hoodoo Wash as the point of interconnection, all in Yuma County, AZ.

4active projects
1,260active MW
7total filed
Queue IDProjectkVMWResourceStatus
Q227 Not reported 500 500 Hybrid Operational
Q310 Not reported 500 450 Hybrid Active
Q247 Not reported 500 400 Solar Withdrawn
Q406 Not reported 500 400 Battery Withdrawn
Q43 Not reported 500 290 Solar Operational
Q431 Not reported n/r 168 Hybrid Withdrawn
Q246 Not reported n/r 20 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with APS before relying on these figures.