Trilby Wash substation interconnection queue

3 active projects totaling 750 MW in the APS queue, plus 2 with terminal status (shown grayed).

5 APS queue filings name Trilby Wash as the point of interconnection, all in Maricopa County, AZ.

3active projects
750active MW
5total filed
Queue IDProjectkVMWResourceStatus
Q465 Not reported 230 300 Hybrid Active
Q446 Not reported 230 250 Hybrid Active
Q504 Not reported 230 250 Battery Withdrawn
Q284 Not reported 230 200 Hybrid Withdrawn
Q409 Not reported 230 200 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with APS before relying on these figures.