Substation Scout

Gainesville

Named in 7 PJM planning documents for 8 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
DOMzone
230 kVkV as printed
13mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Do No Harm (DNH) Analysis
DOM-2020-0026-DNH · s2340.1 & s2340.2
Conceptual $1.5M 12/31/2026 Not printed 2024-10-08
TEAC
Do No Harm (DNH) Analysis
DOM-2022-0045-DNH · s3035.2
Conceptual $139.0M (Total) 12/31/2027 Not printed 2026-09-08*
SRRTEP Southern
Burrell 230kV Delivery - NOVEC
DOM-2022-0046 · s3036
Engineering $16.0M 12/30/2028 20.8 MW 2026-10-06
TEAC
Trident 230kV Delivery - NOVEC
DOM-2023-0012 · s3071
Engineering $15.75 M 09/01/2025 100 MW 2024-10-08
TEAC
Do No Harm Analysis
DOM-2023-0013-DNH
Conceptual $88.0M 06/15/2029 300 MW 2024-12-03
TEAC
Old Limb 230kV Delivery – DEV
DOM-2024-0015 · s3704.1
Engineering $35.0 M 8/01/2027 148 MW 2025-10-08
TEAC
Aphrodite 230kV Delivery - NOVEC
DOM-2024-0061
Cancelled $14M 09/30/2027 100 MW 2026-09-08
TEAC
Do No Harm Analysis
DOM-2024-0063-DNH · s3699.3, s3699.4, s3699.5
Conceptual $24.0M 06/01/2029 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$35.0M → $1.5M 2024-10-08 2024-10-08
Substations named ELK RUN; GAINESVILLE; LOUDOUN; MORRISVILLE; REMINGTON CT; ROLLINS FORD → ELK RUN; GAINESVILLE; REMINGTON CT; ROLLINS FORD 2024-10-08 Not reported
Substations named BRISTERS; HORNBAKER; NOKESVILLE; VINT HILL → BRICKYARD; BRISTERS; CLIFTON; DAWKINS BRANCH; GAINESVILLE; HORNBAKER; NOKESVILLE; RAILROAD; VINT HILL 2024-10-08 Not reported
In-service date 12/30/2028 → 01/02/2026 2026-10-06 Not reported
In-service date 01/02/2026 → 12/30/2028 2024-10-08 2025-10-08
Substations named GAINESVILLE; LOUDOUN; MINT SPRINGS → BURRELL; MINT SPRINGS 2024-10-08 2025-10-08
Substations named DAWKINS BRANCH; DEVLIN; GAINESVILLE; LIBERTY; PEGASUS; RAILROAD; ROLLINS FORD; VINT HILL → DAWKINS BRANCH; DEVLIN; PEGASUS 2024-12-03 2025-10-08
Status engineering (Engineering) → cancelled (Canceled) 2025-10-08 2026-09-08
Substations named APHRODITE → APHRODITE; GAINESVILLE; LOUDOUN 2025-10-08 2026-09-08
Substations named BRICKYARD; CLIFTON; DEVLIN; GAINESVILLE; NOKESVILLE; RAILROAD; ROLLINS FORD; VINT HILL; WHEELER → DEVLIN; GAINESVILLE; VINT HILL; WHEELER 2025-05-06 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 27
Burrell 230kV Delivery - NOVEC No role wording
2026-09-08 TEAC
Item 10 - DOM Supplemental Projects p. 14
Aphrodite 230kV Delivery - NOVEC No role wording
2026-09-08* SRRTEP Southern
Dominion p. 124
Trident 230kV Delivery - NOVEC “Line #2161 (Gainesville – Wheeler)”
2026-09-08* SRRTEP Southern
Dominion p. 4
Do No Harm (DNH) Analysis “At Gainesville, upgrade (2) 230 kV circuit breakers”
230 kV
2026-09-08* SRRTEP Southern
Dominion p. 60
Do No Harm (DNH) Analysis No role wording
2026-09-08* SRRTEP Southern
Dominion p. 63
Burrell 230kV Delivery - NOVEC No role wording
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 63
Do No Harm Analysis No role wording
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 79
Old Limb 230kV Delivery – DEV No role wording
2025-05-06 TEAC
Item 09 - DOM Supplemental Projects p. 13
Do No Harm Analysis No role wording
2024-12-03 TEAC
Item 10 - Dominion Supplemental Projects p. 9
Do No Harm Analysis No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 124
Trident 230kV Delivery - NOVEC No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 4
Do No Harm (DNH) Analysis “At Gainesville, upgrade (2) 230 kV circuit breakers and terminal equipment”
230 kV
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 63
Burrell 230kV Delivery - NOVEC No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.