Substation Scout

Heathcote

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to October 8, 2025.

Existingdescribed as
DOMzone
230 kVkV as printed
3mentions

Also printed as: Heathcote substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Daves Store 230kV Delivery - DEV
DOM-2023-0009
Engineering $40.0 M 06/01/2025 100 MW 2024-10-08
TEAC
Old Limb 230kV Delivery – DEV
DOM-2024-0015 · s3704.1
Engineering $35.0 M 8/01/2027 148 MW 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named BRADDOCK; DAVES STORE; HEATHCOTE; IDYLWOOD → DAVES STORE; HEATHCOTE 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Southern
Dominion p. 116
Daves Store 230kV Delivery - DEV “existing Heathcote substation”
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 79
Old Limb 230kV Delivery – DEV No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 116
Daves Store 230kV Delivery - DEV “existing Heathcote substation”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this