Substation Scout

Wheeler

Named in 4 PJM planning documents for 3 projects, from October 8, 2024 to October 8, 2025.

Existingdescribed as
DOMzone
230 kVkV as printed
6mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Do No Harm (DNH) Analysis
DOM-2022-0046-DNH & DOM-2022-0047-DNH
Conceptual $114.0M 12/31/2027 Not printed 2024-10-08
TEAC
Trident 230kV Delivery - NOVEC
DOM-2023-0012 · s3071
Engineering $15.75 M 09/01/2025 100 MW 2024-10-08
TEAC
Do No Harm Analysis
DOM-2024-0063-DNH · s3699.3, s3699.4, s3699.5
Conceptual $24.0M 06/01/2029 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $37.5M → $23.0M 2026-10-06 Not reported
Cost estimate
prior value printed on the same page
$115.0M → $114.0M 2024-10-08 2024-10-08
Cost estimate $114.0M → $37.5M 2024-10-08 2026-10-06
Cost estimate
prior value printed on the same page
$23 → $37.5M 2026-10-06 2026-10-06
Substations named ANDERSON BRANCH; BRISTERS; NOKESVILLE → BRISTERS; LIBERTY; LOUDOUN; MEADOWBROOK; MORRISVILLE; NOKESVILLE; REMINGTON CT; ROLLINS FORD; VINT HILL; WHEELER; WISHING STAR 2026-10-06 Not reported
Substations named BRISTERS; LIBERTY; LOUDOUN; MEADOWBROOK; MORRISVILLE; NOKESVILLE; REMINGTON CT; ROLLINS FORD; VINT HILL; WHEELER; WISHING STAR → ANDERSON BRANCH; BRISTERS; NOKESVILLE 2024-10-08 2026-10-06
Substations named BRICKYARD; CLIFTON; DEVLIN; GAINESVILLE; NOKESVILLE; RAILROAD; ROLLINS FORD; VINT HILL; WHEELER → DEVLIN; GAINESVILLE; VINT HILL; WHEELER 2025-05-06 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Southern
Dominion p. 124
Trident 230kV Delivery - NOVEC “Line #2161 (Gainesville – Wheeler)”
2026-09-08* SRRTEP Southern
Dominion p. 84
Do No Harm (DNH) Analysis No role wording
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 63
Do No Harm Analysis No role wording
2025-05-06 TEAC
Item 09 - DOM Supplemental Projects p. 13
Do No Harm Analysis No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 124
Trident 230kV Delivery - NOVEC No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 84
Do No Harm (DNH) Analysis No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this