Hornbaker
Named in 5 PJM planning documents for 5 projects, from October 8, 2024 to October 6, 2026.
Newdescribed as
DOMzone
230 kV, 230kVkV as printed
9mentions
Described as new: “a new substation (Hornbaker)” — source, page 58
Also printed as: Hornbaker Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Nokesville – Hornbaker Bristow New 230kV Line b4000.322 – b4000.324 |
Not printed | $18.14M | 6/1/2029 | Not printed | 2026-10-06 TEAC |
| Hornbaker 230kV Delivery - NOVEC DOM-2022-0045 · s3035.1 |
Engineering | $45.0M | 12/30/2025 | 150.0 MW | 2024-10-08 TEAC |
| Do No Harm (DNH) Analysis DOM-2022-0045-DNH · s3035.2 |
Conceptual | $139.0M | 12/31/2027 | Not printed | 2024-10-08 TEAC |
| Pegasus 230kV Delivery – NOVEC DOM-2024-0047 · s3700 |
Engineering | $28.5M | 04/14/2027 | 87.0 MW | 2025-10-08 TEAC |
| Bristow 230kV Delivery – NOVEC DOM-2024-0063 · s3699 |
Engineering | $14.0M | 04/30/2028 | 213.0 MW | 2025-10-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Substations named | BRISTERS; HORNBAKER; NOKESVILLE; VINT HILL → BRICKYARD; BRISTERS; CLIFTON; DAWKINS BRANCH; GAINESVILLE; HORNBAKER; NOKESVILLE; RAILROAD; VINT HILL | 2024-10-08 | Not reported |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Item 16 - Reliability Analysis Update - Presentation p. 11 |
Nokesville – Hornbaker Bristow New 230kV Line | “directly adjacent to Hornbaker” |
| 2026-09-08* | SRRTEP Southern Dominion p. 58 |
Hornbaker 230kV Delivery - NOVEC | “a new substation (Hornbaker)” |
| 2026-09-08* | SRRTEP Southern Dominion p. 61 |
Do No Harm (DNH) Analysis | No role wording |
| 2025-10-08 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 13 |
Pegasus 230kV Delivery – NOVEC | No role wording |
| 2025-10-08 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 15 |
Bristow 230kV Delivery – NOVEC | “adjacent to Hornbaker Substation” 230 kV |
| 2024-12-03 | TEAC Item 10 - Dominion Supplemental Projects p. 11 |
Pegasus 230kV Delivery – NOVEC | No role wording |
| 2024-12-03 | TEAC Item 10 - Dominion Supplemental Projects p. 13 |
Bristow 230kV Delivery – NOVEC | “Due to being directly adjacent to Hornbaker Substation” 230 kV |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 58 |
Hornbaker 230kV Delivery - NOVEC | “DP Request for a new substation (Hornbaker)” 230kV |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 61 |
Do No Harm (DNH) Analysis | No role wording 230 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.