White Valley

Named in 2 PJM planning documents for 2 projects, from December 13, 2024 to September 18, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
2mentions

Also printed as: White Valley Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Misoperation Relay Projects
APS-2024-098 to 105, APS-2024-111 to 114, APS-2024-116, APS-2024-118
Not printed Not printed Not printed Not printed 2024-12-13
SRRTEP Western
Misoperation Relays
APS-2024-103
Conceptual $4.63 M 12/31/2029 Not printed 2026-09-18
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-09-18 SRRTEP Western
Item 01 - APS Supplemental Projects p. 7
Misoperation Relays “At White Valley Substation, replace circuit breaker, disconnect switches, substation conductors, wave trap, CVT and relaying”
2024-12-13 SRRTEP Western
Item 15 - APS Supplemental Project p. 6
Misoperation Relay Projects No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.