Shady Oaks Wind Power Project
PJM queue ID AD2-134
Shady Oaks Wind Power Project (AD2-134) is listed in the PJM interconnection queue as a 21.2 MW wind project in Lee County, IL. The filing names Shady Oaks as its point of interconnection. PJM lists its status as “Partially in Service - Under Construction”, with a target commercial operation date of December 7, 2027.
| Queue ID | AD2-134 |
|---|---|
| Project name | Shady Oaks Wind Power Project |
| Status (as published) | Partially in Service - Under Construction |
| Substation | Shady Oaks |
| Point of interconnection | Shady Oaks |
| County | Lee |
| State | IL |
| Voltage | Not reported |
| Capacity | 21.2 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2027-12-07 |
| Source dataset | serial |
Same substation and county
Shady Oaks substation: 2 requests in the PJM queue, 1 active totaling 21.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AG1-128 | Shady Oaks 138 kV | 51.8 | Wind | Withdrawn |
Lee, IL: 106 requests in the PJM queue, 30 active totaling 2,565.3 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 105.9 |
| MW capacity | 21.2 |
| MFO | 215.4 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.