Blooming Grove Solar Energy Center
PJM queue ID AE1-205
Blooming Grove Solar Energy Center (AE1-205) is listed in the PJM interconnection queue as a 84 MW solar project in Livingston County, IL. The filing names McLean as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of December 29, 2028.
| Queue ID | AE1-205 |
|---|---|
| Project name | Blooming Grove Solar Energy Center |
| Status (as published) | Engineering and Procurement |
| Substation | McLean |
| Point of interconnection | McLean 345 kV |
| County | Livingston |
| State | IL |
| Voltage | 345 kV |
| Capacity | 84 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-12-29 |
| Source dataset | serial |
Same substation and county
McLean substation: 5 requests in the PJM queue, 4 active totaling 264 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-1164 | McLean 345 kV | 97.5 | Wind | Active |
| AF2-225 | Bright Stalk Generating Facility | 63 | Solar | EP |
| AE2-223 | Bright Stalk Generating Facility | 19.5 | Wind | EP |
| AE2-173 | Blooming Grove Solar Energy Center | 50 | Battery | Withdrawn |
Livingston, IL: 47 requests in the PJM queue, 13 active totaling 1,544.4 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 200 |
| MW capacity | 84 |
| MFO | 200 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.