Comstock Meadows
In NV Energy’s Annual Progress Report to the Western Electricity Coordinating Council, project “West Tracy - Comstock Meadows 345 kV line”.
Expansion at an existing substation: new voltage level. The quoted wording describes a yard, bus or conversion at a voltage this substation is not otherwise shown at. “This project comprises of 345 kV addition at Comstock Meadow substation with addition of two (2) 345/120kV transformers to accommodate rapid load growth in the Reno TRIC area.” — NV Energy 2026 Annual Progress Report, p.3
Existing station: The same report has a 120 kV line out of Comstock Meadows Substation (the Redwood Materials project, phase 1 energized November 2024), and the 345 kV addition comes with 345/120 kV transformers; 345 kV is a new voltage there. “This project is comprised of a new 120 kV line out of Comstock Meadows Substation” — NV Energy 2026 Annual Progress Report, p.2
Also printed as: Comstock Meadow
Note. Greenlink West adds two 40-mile 345 kV lines from Walker River to Comstock Meadows, and a new Lantern - Comstock Meadows 345 kV line is planned for Sierra Solar phase 2 (2028).
The progress report prints no county for this substation, and none has been found printed for it elsewhere yet.
Source: WECC Annual Progress Reports filed with the WECC Studies Subcommittee: NV Energy 2026 Annual Progress Report (dated March 4, 2026); NV Energy 2025 Annual Progress Report (dated February 3, 2025); GridLiance West 2026 Annual Progress Report (dated March 13, 2026). Retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- The WECC Annual Progress Reports print no county for a substation. A county shown here is printed for that station elsewhere; otherwise it is left blank.
- WECC asks for transmission additions over 200 kV, generation of 200 MW or more, and smaller facilities that may have a significant regional impact (the thresholds as Valley Electric’s 2026 report states them). NV Energy also lists many 120 kV and 138 kV projects, but a substation missing from a report may still be planned.
- An in-service date is the one the report prints, not a construction schedule.