Lantern
In NV Energy’s Annual Progress Report to the Western Electricity Coordinating Council, project “Sierra Solar, Lantern 345 kV Substation and Lantern - Comstock Meadows 345 kV line”.
Described as new. The quoted wording calls this substation new. “The new Lantern 345 kV substation will be a new generation collector substation” — NV Energy 2026 Annual Progress Report, p.1
Also mentioned: “interconnection at NV Energy's proposed Lantern 345 kV substation that was proposed for Sierra Solar interconnection” — NV Energy 2026 Annual Progress Report, p.5
Note. The report says Lantern folds into the Valmy - East Tracy 345 kV line #3422 and will interconnect NV Energy's Sierra Solar phases 1 and 2 (400 MW and 600 MW of solar and battery). Fervo Energy's 115 MW Corsac geothermal project is also proposed to interconnect at Lantern (in service June 2036, as printed).
The progress report prints no county for this substation, and none has been found printed for it elsewhere yet.
Location
Churchill County, NV
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. No source read prints the switchyard's coordinates or parcel. The Sierra Solar plant is on Churchill County APNs 004-351-03, -11, -15, -09, -22 and -05 on both sides of Sage Hen Creek Road (Nevada Department of Taxation fiscal note), but the switchyard sits on the Valmy-Tracy line at the end of the gen-tie, not necessarily on those parcels. OSM has no substation named Lantern (extract 2026-11-20).
Sources: NV Energy 2026 Annual Progress Report to WECC (2026), p.1 · NV Energy 2027-2046 Integrated Resource Plan, Volume 8 of 41, Narrative Supply Plan (PUCN Docket No. 26-05___) (2026), printed pp.13-14 · BLM completes environmental assessment for the Sierra Solar Utilities Project (2024-12-20) · Nevada Department of Taxation fiscal note, Sierra Solar Phase 1 renewable energy abatement (2024), p.1. Researched by Substation Scout; checked November 21, 2026.
Generation interconnection requests filed in Churchill, NV: NV Energy queue, 18 active of 30. Same county, not the same substation.
Source: WECC Annual Progress Reports filed with the WECC Studies Subcommittee: NV Energy 2026 Annual Progress Report (dated March 4, 2026); NV Energy 2025 Annual Progress Report (dated February 3, 2025); GridLiance West 2026 Annual Progress Report (dated March 13, 2026). Retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- The WECC Annual Progress Reports print no county for a substation. A county shown here is printed for that station elsewhere; otherwise it is left blank.
- WECC asks for transmission additions over 200 kV, generation of 200 MW or more, and smaller facilities that may have a significant regional impact (the thresholds as Valley Electric’s 2026 report states them). NV Energy also lists many 120 kV and 138 kV projects, but a substation missing from a report may still be planned.
- An in-service date is the one the report prints, not a construction schedule.