Trout Canyon
In GridLiance West’s Annual Progress Report to the Western Electricity Coordinating Council, project “GLW 230 kV Revised Upgrades - CAISO 2022-2023 TPP”.
Expansion at an existing substation: new voltage level. The quoted wording describes a yard, bus or conversion at a voltage this substation is not otherwise shown at. “Install a new Trout Canyon 500 kV bus and three 500/230 kV transformers at Trout Canyon.” — GridLiance West 2026 Annual Progress Report, p.2
Existing station: The same report has Trout Canyon on GridLiance West's 230 kV system (Pahrump - Gamebird - Trout Canyon); a 500 kV bus is a new voltage there. “Rebuild to 230 kV double circuit from Pahrump to Gamebird to Trout Canyon.” — GridLiance West 2026 Annual Progress Report, p.3
Note. The report also rebuilds the Trout Canyon - Sloan Canyon lines to 500 kV double circuit.
The progress report prints no county for this substation, and none has been found printed for it elsewhere yet.
Source: WECC Annual Progress Reports filed with the WECC Studies Subcommittee: NV Energy 2026 Annual Progress Report (dated March 4, 2026); NV Energy 2025 Annual Progress Report (dated February 3, 2025); GridLiance West 2026 Annual Progress Report (dated March 13, 2026). Retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- The WECC Annual Progress Reports print no county for a substation. A county shown here is printed for that station elsewhere; otherwise it is left blank.
- WECC asks for transmission additions over 200 kV, generation of 200 MW or more, and smaller facilities that may have a significant regional impact (the thresholds as Valley Electric’s 2026 report states them). NV Energy also lists many 120 kV and 138 kV projects, but a substation missing from a report may still be planned.
- An in-service date is the one the report prints, not a construction schedule.