Beatty
In GridLiance West’s Annual Progress Report to the Western Electricity Coordinating Council, project “GLW Beatty Area 230 kV Project - CAISO 2022-2023 TPP”.
Expansion at an existing substation: new voltage level. The quoted wording describes a yard, bus or conversion at a voltage this substation is not otherwise shown at. “Expand existing Beatty, Lathrop, Valley Switch and Vista 138 kV substations to 230 kV” — GridLiance West 2026 Annual Progress Report, p.3
Existing station: The report prints Beatty as an existing 138 kV substation expanded to 230 kV. “Expand existing Beatty, Lathrop, Valley Switch and Vista 138 kV substations to 230 kV” — GridLiance West 2026 Annual Progress Report, p.3
Note. The report also builds a 32-mile Beatty - Lathrop 230 kV line next to the existing 138 kV line.
The progress report prints no county for this substation, and none has been found printed for it elsewhere yet.
Source: WECC Annual Progress Reports filed with the WECC Studies Subcommittee: NV Energy 2026 Annual Progress Report (dated March 4, 2026); NV Energy 2025 Annual Progress Report (dated February 3, 2025); GridLiance West 2026 Annual Progress Report (dated March 13, 2026). Retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- The WECC Annual Progress Reports print no county for a substation. A county shown here is printed for that station elsewhere; otherwise it is left blank.
- WECC asks for transmission additions over 200 kV, generation of 200 MW or more, and smaller facilities that may have a significant regional impact (the thresholds as Valley Electric’s 2026 report states them). NV Energy also lists many 120 kV and 138 kV projects, but a substation missing from a report may still be planned.
- An in-service date is the one the report prints, not a construction schedule.