Substation Scout

Robinson Summit

In NV Energy’s Annual Progress Report to the Western Electricity Coordinating Council, project “Greenlink Nevada North (GLN)”.

Not printedcounty (not printed)
525, 230kV as printed
NVEreport
December 2028 (Greenlink North, as printed)in service, as printed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “The project also includes an expansion of the existing Robinson Summit 525/230 kV substation” — NV Energy 2026 Annual Progress Report, p.3

Note. The eastern end of Greenlink North. Great Basin Transmission's 2026 report also plans SWIP-North, a 500 kV line from Idaho Power's Midpoint substation to Robinson Summit (near Ely), with phase-shifting transformers and capacitors at Robinson Summit.

The progress report prints no county for this substation, and none has been found printed for it elsewhere yet.

Source: WECC Annual Progress Reports filed with the WECC Studies Subcommittee: NV Energy 2026 Annual Progress Report (dated March 4, 2026); NV Energy 2025 Annual Progress Report (dated February 3, 2025); GridLiance West 2026 Annual Progress Report (dated March 13, 2026). Retrieved 2026-11-21; records reviewed by hand 2026-11-21.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first