Sagebrush
In NV Energy’s Annual Progress Report to the Western Electricity Coordinating Council, project “Greenlink Nevada West (GLW)”.
Described as new. The quoted wording calls this substation new. “construction of the new Sagebrush (f.k.a., Amargosa) 525 kV collector station” — NV Energy 2026 Annual Progress Report, p.8
Also printed as: Amargosa
Note. Formerly known as Amargosa, the report says. A collector station on Greenlink West, the 320-mile 525 kV line from Northwest Substation (Las Vegas) to Walker River (Yerington).
The progress report prints no county for this substation, and none has been found printed for it elsewhere yet.
Location
Nye County, NV
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. The selected site, AS-1, is placed only in words: "approximately 12.2 miles west of the US 95/SR 373 junction". The 2021 Plan of Development prints a coordinate for the Amargosa Substation (36.657176, -116.510487), but that is the Proposed Action site, which the ROD describes as AS-2, "approximately 6.1 miles west of the US 95/SR 373 junction"; the BLM selected AS-1 instead, so the printed coordinate is not this station. NV Energy's April 2024 project map draws "SAGEBRUSH SUBSTATION" south of Beatty along US 95 at 1:2,000,000, too coarse for a point.
Note: The 2021 Plan of Development coordinate (36.657176, -116.510487, Census county Nye) is the not-selected AS-2 site; kept out of the record's point.
Sources: NV Energy 2026 Annual Progress Report to WECC (2026), p.8 · Greenlink West Transmission Project Record of Decision and Approved Resource Management Plan Amendments (BLM, joint with DOE/NNSA, DOE/EIS-0564) (September 2024), PDF p.24 · NDEP Clean Water Act Section 401 application, Greenlink West Transmission Project (NV Energy), with Project Location map (map dated 2024-04-05), p.5 · NV Energy, Greenlink North Transmission Project presentation to the White Pine County Board of County Commissioners (March 25, 2026), slide 3. Researched by Substation Scout; checked November 21, 2026.
Generation interconnection requests filed in Nye, NV: NV Energy queue, 6 active of 22. Same county, not the same substation.
Source: WECC Annual Progress Reports filed with the WECC Studies Subcommittee: NV Energy 2026 Annual Progress Report (dated March 4, 2026); NV Energy 2025 Annual Progress Report (dated February 3, 2025); GridLiance West 2026 Annual Progress Report (dated March 13, 2026). Retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- The WECC Annual Progress Reports print no county for a substation. A county shown here is printed for that station elsewhere; otherwise it is left blank.
- WECC asks for transmission additions over 200 kV, generation of 200 MW or more, and smaller facilities that may have a significant regional impact (the thresholds as Valley Electric’s 2026 report states them). NV Energy also lists many 120 kV and 138 kV projects, but a substation missing from a report may still be planned.
- An in-service date is the one the report prints, not a construction schedule.