Named in 2 PJM planning documents for 3 projects, on October 8, 2024.

Newdescribed as
DOMzone
230kVkV as printed
6mentions

Described as new: “proposed Sycolin Creek Substation” — source, page 77

Also printed as: Sycolin Creek Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Sycolin Creek 230kV Delivery - DEV
DOM-2022-0042 · s3048
Engineering $28.0 M 06/15/2026 100MW 2024-10-08
TEAC
Lunar 230kV Delivery - DEV
DOM-2022-0054 · s3074
Engineering $28.0 M 08/01/2026 100MW 2024-10-08
TEAC
Starlight 230kV Delivery - DEV
DOM-2023-0001 · s3076
Engineering $28.0 M 06/01/2028 100MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Southern
Dominion p. 108
Starlight 230kV Delivery - DEV No role wording
2026-09-08* SRRTEP Southern
Dominion p. 77
Sycolin Creek 230kV Delivery - DEV “proposed Sycolin Creek Substation”
230kV
2026-09-08* SRRTEP Southern
Dominion p. 96
Lunar 230kV Delivery - DEV No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 108
Starlight 230kV Delivery - DEV No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 76
Sycolin Creek 230kV Delivery - DEV “new substation (Sycolin Creek)”
230kV
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 96
Lunar 230kV Delivery - DEV No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.