Substation Scout

Idylwood

Named in 4 PJM planning documents for 5 projects, from October 8, 2024 to October 6, 2026.

Not stateddescribed as
DOMzone
—kV as printed
8mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Do No Harm Analysis
DOM-2021-0016-DNH · s2609.2
In service $40.0 M 12/15/2023 Not printed 2024-10-08
TEAC
Do No Harm (DNH) Analysis
DOM-2022-0001-DNH & DOM-2022-0041-DNH · s3040
Conceptual $43.5M 06/30/2027 Not printed 2024-10-08
TEAC
Daves Store 230kV Delivery - DEV
DOM-2023-0009
Engineering $40.0 M 06/01/2025 100 MW 2024-10-08
TEAC
Do No Harm (DNH) Analysis
DOM-2023-0009-DNH · s3068.2
Conceptual $33.5M 12/31/2026 Not printed 2026-09-08*
SRRTEP Southern
Dominion Transmission Zone: Supplemental Line #2035 EOL Partial Rebuild
DOM-2026-0036
Conceptual $44M 03/15/2029 60MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named BRADDOCK; DAVES STORE; HEATHCOTE; IDYLWOOD → DAVES STORE; HEATHCOTE 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 14 - DOM Supplemental Projects - Presentation p. 9
Dominion Transmission Zone: Supplemental Line #2035 EOL Partial Rebuild No role wording
2026-09-08 TEAC
Item 10 - DOM Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Line #2035 EOL Partial Rebuild No role wording
2026-09-08* SRRTEP Southern
Dominion p. 118
Do No Harm (DNH) Analysis No role wording
2026-09-08* SRRTEP Southern
Dominion p. 16
Do No Harm Analysis No role wording
2026-09-08* SRRTEP Southern
Dominion p. 67
Do No Harm (DNH) Analysis No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 118
Daves Store 230kV Delivery - DEV No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 16
Do No Harm Analysis No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 67
Do No Harm (DNH) Analysis No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.