Substation Scout

Breezy Knoll

Named in 1 PJM planning document for 1 project, on December 5, 2023.

Work described at itdescribed as
DOMzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

Part of a named transmission project: 2022 Window 3 Northern Virginia/Doubs Cluster ($1,418.3M).

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster
B3800.230 – B3800.242
Not printed $78.4 M 12/1/2027 Not printed 2023-12-05
TEAC

Other substations in this project

“2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster” also names 9 other substations, with what the most recent document says about each.

Every mention

DateDocumentProjectWhat the document says about it
2023-12-05 TEAC
Item 15 - Reliability Analysis Update 2022 Window 3 p. 45
2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster “Relay resets/revisions at the following substations: – Breezy Knoll”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.