Substation Scout

Locks

Named in 4 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.

Not stateddescribed as
DOMzone
—kV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Do No Harm Analysis
DOM-2021-0016-DNH · s2609.2
In service $40.0 M 12/15/2023 Not printed 2024-10-08
TEAC
Dominion Transmission Zone: Supplemental Do No Harm Analysis
DOM-2024-0036-DNH (Update)
Conceptual $212M Q4 2031 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 14 - DOM Supplemental Projects - Presentation p. 5
Dominion Transmission Zone: Supplemental Do No Harm Analysis No role wording
2026-09-08* SRRTEP Southern
Dominion p. 16
Do No Harm Analysis No role wording
2026-07-07 TEAC
Item 14 - DOM Supplemental Projects p. 9
Dominion Transmission Zone: Supplemental Do No Harm Analysis No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 16
Do No Harm Analysis No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this