Named in 1 PJM planning document for 1 project, on Not reported.

Newdescribed as
AEPzone
—kV as printed
1mentions

Described as new: “new Chinstrap (customer) station” — source, page 150

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Central/NW OH, Indiana.
AEP-2022-OH023, AEP-2022-OH034, AEP-2022-OH036, AEP-2022-OH045, AEP-2022-OH046, AEP-2022-OH075, AEP-2022-OH077, AEP-2023-OH016, AEP-2023-OH019, AEP-2023-OH032, AEP-2023-OH040, AEP-2023-OH044, AEP-2023-OH052, AEP-2023-OH063 · s3442.1-.30
Conceptual $378.3M 10/13/2027 968 MW 2026-09-08*
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 150
Central/NW OH, Indiana. “new Chinstrap (customer) station”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.