Substation Scout

Kirk substation interconnection queue

1 active project totalling 64.6 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
64.6active MW
3total filed
Queue IDProjectkVMWResourceStatus
AF2-122 Union Ridge Solar 138 64.6 Solar Partially in Service - Under Construction
AH1-325 Kirk 138 kV 138 50 Battery Withdrawn
Z1-063 Kirk 34.5kV 34.5 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.