Curleys

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to April 7, 2026.

Newdescribed as
AEPzone
345 kVkV as printed
3mentions

Described as new: “new 345 kV Curleys station” — source, page 138

Also printed as: Curleys station · Curleys substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Central/NW OH, Indiana.
AEP-2022-OH023, AEP-2022-OH034, AEP-2022-OH036, AEP-2022-OH045, AEP-2022-OH046, AEP-2022-OH075, AEP-2022-OH077, AEP-2023-OH016, AEP-2023-OH019, AEP-2023-OH032, AEP-2023-OH040, AEP-2023-OH044, AEP-2023-OH052, AEP-2023-OH063 · s3442.1-.30
Conceptual $378.3M 10/13/2027 Not printed 2024-10-08
TEAC
Corridor, OH
AEP-2026-OH019
Not printed Not printed Not printed 638 MW 2026-04-07
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 138
Central/NW OH, Indiana. “new 345 kV Curleys station”
345 kV
2026-04-07 TEAC
Item 04 - AEP Supplemental Projects p. 8
Corridor, OH “ongoing Curleys substation project”
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 138
Central/NW OH, Indiana. “to a new 345 kV Curleys station”
345 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.