Substation Scout

Babbitt

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
AEPzone
138 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Central/NW OH, Indiana.
AEP-2022-OH023, AEP-2022-OH034, AEP-2022-OH036, AEP-2022-OH045, AEP-2022-OH046, AEP-2022-OH075, AEP-2022-OH077, AEP-2023-OH016, AEP-2023-OH019, AEP-2023-OH032, AEP-2023-OH040, AEP-2023-OH044, AEP-2023-OH052, AEP-2023-OH063 · s3442.1-.30
Conceptual $378.3M 10/13/2027 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 154
Central/NW OH, Indiana. “Babbitt 138 kV: Replace (2) 63 kA bus-tie circuit breakers”
138 kV
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 154
Central/NW OH, Indiana. “Replace (2) 63 kA bus-tie circuit breakers with 80 kA circuit breakers”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.