Substation Scout

Salem 500kV

PJM queue ID AH1-710

Salem 500kV (AH1-710) is listed in the PJM interconnection queue as a 228.2 MW nuclear project in Salem County, NJ. The filing names Salem as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of October 22, 2027.

Queue IDAH1-710
Project nameSalem 500kV
Status (as published)Active
SubstationSalem
Point of interconnectionSalem 500kV
CountySalem
StateNJ
Voltage500 kV
Capacity228.2 MW
Resource (as published)Nuclear
Resource categoryNuclear (normalized for filtering)
Target commercial operation2027-10-22
Source datasetcycle

Same substation and county

Salem substation: 5 requests in the PJM queue, 3 active totaling 369.2 MW.

Queue IDProjectMWResourceStatus
H17Salem 1 & 2115NuclearIn Service
C07Salem 1 & 226NuclearIn Service
K01Mannington Mills Units 1,2,38OtherDeactivated
X1-083Salem 12kV2.3SolarWithdrawn

Salem, NJ: 114 requests in the PJM queue, 13 active totaling 906.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperPSEG Nuclear LLC
Transmission ownerPSEG
Project typeGeneration Interconnection
CycleTC2
StagePhase 3
MW energy256.8
MW capacity228.2
MFO2650.8
Submitted date4/9/2025
Last updated9/10/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.