Substation Scout

Parlin 230 kV

PJM queue ID C01-1075

Queue IDC01-1075
Project nameParlin 230 kV
Status (as published)Active
SubstationParlin
Point of interconnectionParlin 230 kV
CountyMiddlesex
StateNJ
Voltage230 kV
Capacity102 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2027-06-30
Source datasetcycle

Additional filed fields

DeveloperJVS Energy LLC
Transmission OwnerJCPL
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy102.0
Mw Capacity102.0
Mfo102.0
Submitted Date4/27/2026
Last Updated5/28/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.