Keystone substation interconnection queue

4 active projects totalling 86 MW in the PJM queue, plus 8 with terminal status (shown greyed).

4active projects
86active MW
12total filed
Queue IDProjectkVMWResourceStatus
B10 Keystone 500kV 500 600 Gas Withdrawn
D23 Keystone 500kV 500 500 Gas Withdrawn
B07 Keystone 500kV 500 300 Gas Withdrawn
AG1-549 Keystone 230 kV 230 85 Hybrid Withdrawn
G51 Keystone 500kV 500 75 Gas Withdrawn
V3-015 Wells County Wind Farm 345 39 Wind Withdrawn
V4-021 Keystone 345kV 345 39 Wind Withdrawn
Q10 Montpelier 345 27 Gas In Service
T109 Keystone Generating Station 500 20 Coal In Service
T110 Keystone Generating Station 500 20 Coal In Service
S13 Montpelier 345 19 Gas In Service
Y2-112 Keystone 345kV 345 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.