Substation Scout

Blairsville East substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
C01-2156 Blairsville East 138 kV 138 50 Battery Withdrawn
AG1-295 Blairsville East 23 kV 23 4.9 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.