Keystone Generating Station
PJM queue ID T110
Keystone Generating Station (T110) is listed in the PJM interconnection queue as a 20 MW coal project in Indiana County, PA. The filing names Keystone as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of August 23, 2010.
| Queue ID | T110 |
|---|---|
| Project name | Keystone Generating Station |
| Status (as published) | In Service |
| Substation | Keystone |
| Point of interconnection | Keystone 500kV |
| County | Indiana |
| State | PA |
| Voltage | 500 kV |
| Capacity | 20 MW |
| Resource (as published) | Coal |
| Resource category | Coal (normalized for filtering) |
| Target commercial operation | 2010-08-23 |
| Source dataset | serial |
Same substation and county
Keystone substation: 12 requests in the PJM queue, 4 active totaling 86 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| Q10 | Montpelier | 27 | Gas | In Service |
| T109 | Keystone Generating Station | 20 | Coal | In Service |
| S13 | Montpelier | 19 | Gas | In Service |
| B10 | Keystone 500kV | 600 | Gas | Withdrawn |
| D23 | Keystone 500kV | 500 | Gas | Withdrawn |
| B07 | Keystone 500kV | 300 | Gas | Withdrawn |
| AG1-549 | Keystone 230 kV | 85 | Hybrid | Withdrawn |
| G51 | Keystone 500kV | 75 | Gas | Withdrawn |
| V3-015 | Wells County Wind Farm | 39 | Wind | Withdrawn |
| V4-021 | Keystone 345kV | 39 | Wind | Withdrawn |
| Y2-112 | Keystone 345kV | 0 | Battery | Withdrawn |
Indiana, PA: 33 requests in the PJM queue, 11 active totaling 4,617.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 20 |
| MW capacity | 20 |
| MFO | 916 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.