Substation Scout

Piney - Timblin substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
AH2-129 Piney - Timblin 115 kV 115 23.8 Solar Withdrawn
AH1-372 Piney - Timblin 115 kV 115 10.9 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.