Kittanning-Rural Valley substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Kittanning-Rural Valley as the point of interconnection, all in Armstrong County, PA.
Target commercial operation dates as filed run from Apr 2023 to Jun 2025 (2 filings).
Transmission owner as filed: APS (1 filing).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-386 | Kittanning-Rural Valley 25 kV | 25 | 18 | Solar | Withdrawn | Apr 2023 |
| AI2-323 | Kittanning-Rural Valley 25 kV | 25 | 7.6 | Solar | Withdrawn | Jun 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Armstrong County, PA
- South Bend: 8 active, 1,446.8 MW of 12 filed
- Keystone: 4 active, 86 MW of 12 filed
- Timblin: 1 active, 20 MW of 3 filed
- Clementine-Clementine Jct.: none active of 2 filed
- Keystone-Conemaugh: none active of 2 filed
- Piney - Timblin: none active of 2 filed