Garner-Northern Neck substation interconnection queue
3 active projects totalling 145.4 MW in the PJM queue, plus 3 with terminal status (shown greyed).
3active projects
145.4active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AE1-155 | Bookers Mill Solar | 115 | 76.2 | Solar | In Service |
| AI2-279 | Garner-Northern Neck 115 kV | 115 | 43 | Battery | Withdrawn |
| AF2-036 | Garner-Northern Neck 115 kV | 115 | 37.2 | Solar | Withdrawn |
| AF2-120 | Cerulean Solar and Mulberry BESS | 115 | 37.2 | Solar | UC-ISP |
| AG1-536 | Cerulean Solar and Mulberry BESS | 115 | 32 | Battery | EP |
| AI2-275 | Garner-Northern Neck 115 kV | 115 | 5 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.