Smith Mountain-Bearskin substation interconnection queue
2 active projects totalling 45.6 MW in the PJM queue, plus 1 with terminal status (shown greyed).
2active projects
45.6active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AC1-083 | Maplewood Solar | 138 | 38 | Solar | In Service |
| AI2-271 | Smith Mountain-Bearskin 138 kV | 138 | 14.4 | Solar | Withdrawn |
| AD1-017 | Maplewood Solar | 138 | 7.6 | Solar | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.