Cerulean Solar and Mulberry BESS

PJM queue ID AF2-120

Queue IDAF2-120
Project nameCerulean Solar and Mulberry BESS
Status (as published)UC-ISP
SubstationGarner-Northern Neck
Point of interconnectionGarner-Northern Neck 115 kV
CountyRichmond
StateVA
Voltage115 kV
Capacity37.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2031-05-31
Source datasetcycle

Additional filed fields

DeveloperVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy62.0
Mw Capacity37.2
Mfo62.0
Submitted Date2/28/2020
Last Updated7/20/2026