Garner-Lancaster substation interconnection queue
1 active project totaling 36 MW in the PJM queue, plus 2 with terminal status (shown grayed).
3 PJM queue filings name Garner-Lancaster as the point of interconnection, all in VA.
Target commercial operation dates as filed run from Dec 2019 to Mar 2031 (3 filings). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: Dominion (2 filings).
1active projects
36active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AC1-142 | Garner-Lancaster 115kV | 115 | 57 | Solar | Withdrawn | Dec 2019 |
| AG1-135 | Moon Corner Solar | 115 | 36 | Solar | UC-ISP | Mar 2031 |
| AG2-005 | Garner-Lancaster 115 kV | 115 | 8.4 | Solar | Withdrawn | Dec 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Lancaster County, VA
- Garner DP-Lancaster: 3 active, 68.7 MW of 7 filed
- Garner Delivery Point - Lancaster: none active of 2 filed
Other PJM queue substations in Richmond County, VA
- Garner-Northern Neck: 3 active, 145.4 MW of 6 filed
- Northern Neck: 3 active, 8.4 MW of 6 filed
- Westmoreland - Oak Grove: none active of 3 filed