Substation Scout

Richmond, VA interconnection queue

5 active projects totalling 223.2 MW in the PJM queue, plus 6 with terminal status (shown greyed).

5active projects
223.2active MW
11total filed
Queue IDProjectkVMWResourceStatus
AI1-183 DuPont - Marlboro 115 kV 115 130 Battery Withdrawn
AI1-031 Westmoreland - Oak Grove 230kV 230 100 Battery Withdrawn
C01-1106 Moon Corner 115 kV 115 88 Battery Active
AI2-279 Garner-Northern Neck 115 kV 115 43 Battery Withdrawn
AF2-036 Garner-Northern Neck 115 kV 115 37.2 Solar Withdrawn
AF2-120 Cerulean Solar and Mulberry BESS 115 37.2 Solar UC-ISP
AG1-135 Moon Corner Solar 115 36 Solar UC-ISP
AG1-536 Cerulean Solar and Mulberry BESS 115 32 Battery EP
C01-1104 Robley 115 kV 115 30 Battery Active
AH1-134 Northern Neck 230 kV 230 12 Battery Withdrawn
AG1-210 Haynesville Energy Storage 34.5 4 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.