Substation Scout

Eagle Point

PJM queue ID Y2-105

Eagle Point (Y2-105) is listed in the PJM interconnection queue as a 50 MW gas project in Gloucester County, NJ. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2016.

Queue IDY2-105
Project nameEagle Point
Status (as published)In Service
SubstationEagle Point
Point of interconnectionEagle Point 230kV
CountyGloucester
StateNJ
Voltage230 kV
Capacity50 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2016-06-01
Source datasetserial

Same substation and county

Eagle Point substation: 5 requests in the PJM queue, 2 active totaling 72.9 MW.

Queue IDProjectMWResourceStatus
X1-039Eagle Point22.9GasIn Service
A16Eagle Point 230 kV800GasWithdrawn
W3-125Eagle Point 230kV27.9GasWithdrawn
H26Eagle Point 230kV25GasWithdrawn

Gloucester, NJ: 88 requests in the PJM queue, 22 active totaling 1,788.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy63
MW capacity50
MFO253

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.