Substation Scout

Clubhouse-Sapony substation interconnection queue

1 active project totaling 89 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Clubhouse-Sapony as the point of interconnection, all in VA.

Target commercial operation dates as filed run from Dec 2022 to Feb 2030 (2 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: Dominion (1 filing).

1active projects
89active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE2-033 Enclave Solar Energy Center 230 89 Solar Engineering and Procurement Feb 2030
AF1-266 Clubhouse-Sapony 230 kV 230 74.5 Battery Withdrawn Dec 2022

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Tracked changes at this substation

1 change to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-11-02AE2-033Status changen/a Suspended → Engineering and Procurement

Other PJM queue substations in Sussex County, VA

All 39 PJM queue filings in Sussex County, VA.

Other PJM queue substations in Dinwiddie County, VA

All 20 PJM queue filings in Dinwiddie County, VA.