Dinwiddie, VA interconnection queue

9 active projects totalling 2,405.2 MW in the PJM queue, plus 11 with terminal status (shown greyed).

9active projects
2,405.2active MW
20total filed
Queue IDProjectkVMWResourceStatus
C01-2087 Carson - Rawlings 500kV 500 460.9 Hybrid Active
C01-2094 Carson - Rawlings 500kV 500 453.5 Hybrid Active
C01-2089 Carson - Rawlings 500kV 500 436.1 Hybrid Active
C01-2093 Carson - Rawlings 500kV 500 433.1 Hybrid Active
C01-2090 Carson - Rawlings 500kV 500 421.4 Hybrid Active
AE2-313 Carson-Rawlings 500 kV 500 188.4 Solar Withdrawn
AG1-449 Rawlings-Carson 500 kV 500 122 Battery Withdrawn
C01-1186 Carson 230 kV 230 100 Battery Active
C01-2009 Carson 230 kV 230 100 Battery Active
AE1-235 Carson-Clover 500 kV 500 76 Solar Withdrawn
AF1-266 Clubhouse-Sapony 230 kV 230 74.5 Battery Withdrawn
AE1-249 Reams 115 kV 115 40.1 Hybrid Withdrawn
AG2-506 Carson 230 kV 230 40 Battery Withdrawn
AH2-268 Sapony 34.5 kV 34.5 33.7 Hybrid Withdrawn
AB2-160 Reams Solar 115 30.4 Solar Withdrawn
AG1-393 DW-Lew Jones Solar 34.5 12 Solar Withdrawn
AI2-032 Distribution Circuit#324 34.5 kV 34.5 12 Solar Withdrawn
AF2-108 Locks 34.5 kV 34.5 10 Hybrid Withdrawn
AC1-061 Dinwiddie 2 34.5 0.2 Hybrid In Service
C01-2047 Carson - Rawlings 500 kV 500 0 Not reported Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.